Italy continues to make progress in its energy transition, closing November with a total of 1.2 GW of renewable energy projects in various stages of environmental processing.
While 159.6 MW received a negative evaluation in their environmental impact processing, these include the wind farm promoted by Ecopower Srl (43.6 MW), the photovoltaic system of 96.1 MW by DIOMEDE SRL, the agrivoltaic installation of 19.9 MW by Ambra Solare 28 S.r.l., and another agrivoltaic project by INE MONTEMILONE S.r.l., which does not have a defined capacity.
According to an analysis conducted by Energía Estratégica España based on data from the Ministero dell’Ambiente e della Sicurezza Energetica (MASE), agrovoltaic, wind, and photovoltaic projects have been processed, reflecting a diversification in the technologies under development. Additionally, some plants integrate storage.
Wind technology, with 596.6 MW, leads in capacity, while agrivoltaics, with 528.8 MW, remains key due to its combination of energy and agricultural use.
Wind Leads Installed Capacity
In terms of installed capacity, wind energy was the predominant technology, with 553 MW advancing in environmental processing. Projects such as the Macchitelli Wind Farm (72 MW) by GRV WIND NISSA S.r.l. and the repowering of the “Sant’Agata Wind Park” by Fri-El S. Agata stand out in this category.
Moreover, several developments integrate storage systems, such as the 31 MW park with 8 MW of storage by Vento Solare S.r.l., reflecting a trend toward technological hybridization.
Meanwhile, agrivoltaics continues to establish itself as a strategic technology. In total, 508.9 MW of agrivoltaics were processed, with the 106.4 MW project by R.POWER ITALY SOL S.r.l. being the largest of its kind. This reflects the appeal of this technology for combining renewable generation with agricultural activities.
Photovoltaics advanced in November with 176.6 MW in environmental processing from four projects, while 96 MW were rejected.
Company Participation
GRV and R.POWER ITALY SOL S.r.l. led the business activity with 162 MW and 106.4 MW respectively, contributing projects in agrivoltaics and wind energy.
Meanwhile, Solaria and DUDAIM PROPCO S.R.L. also made their mark with large-scale developments of 82.2 MW and 75.7 MW, respectively. Additionally, notable developers like Iberdrola and Naturgy stand out.
Processing Statuses
An analysis of the processing statuses reveals a mixed picture. Of the total projects, 47% are in the initial “Verifica amministrativa” stage of administrative review.
29% faced environmental impact assessments, with several cases receiving negative opinions. 24% of the plants have made significant progress in the environmental processing process, as they are in the “Provvedimento Unico in materia Ambientale” phase.
The percentage of negative opinions at the environmental impact stage underscores the regulatory challenges developers face, especially for agrivoltaic projects.
It should be noted that grid saturation remains a structural challenge in Italy, with over 300 GW of pending connection requests. According to the operator Terna, urgent reforms in transmission infrastructure are required to avoid bottlenecks that hinder the development of new renewable projects.
List of Projects Advancing in Environmental Processing in November
PROYECTO | TECNOLOGIA | POTENCIA (MW) | PROMOTOR | FECHA | ESTADO |
Guarini | Agrovoltaica | 28,4 | Guarini S.r.l. | 12/11/2024 |
Provvedimento Unico in materia Ambientale
|
“Masseria Sterpara Sottana”. | Agrovoltaica | 19,9 | INE MONTEMILONE S.r.l. | 13/11/2024 | |
Treia Fiorini | Agrovoltaica | 16,9 | Stern PV 4 S.r.l. | 13/11/2024 | |
Sterpara 2 | Agrovoltaica | 19,9 | Ambra Solare 28 S.r.l. | 07/11/2024 |
Valutazione Impatto Ambientale negativa
|
Rotello 52.7 | Agrovoltaica | DS ITALIA 1 S.R.L. | 14/11/2024 |
Valutazione Impatto Ambientale negativa
|
|
“Green and Blue Monte La Rosa | Agrovoltaica | 2,9 | Alter Otto S.r.l. | 05/11/2024 |
Verifica amministrativa
|
Tuscania 3 | Agrovoltaica | 19,6 | Iberdrola Renevables Italia S.p.A. | 11/11/2024 |
Verifica amministrativa
|
“ORT02 | Agrovoltaica | 72,3 | LT 09 S.r.l. | 04/11/2024 |
Verifica amministrativa
|
AGV RAMACCA 2 | Agrovoltaica | 106,4 | R.POWER ITALY SOL S.R.L. | 16/11/2024 |
Verifica amministrativa
|
Progetto di un impianto agrivoltaico di potenza pari a 70,3 MW, con sistema di accumulo da 25 MW e delle relative opere di connessione alla RTN, da realizzarsi nei Comuni di Foggia (FG), in località “Cervaro”, Ascoli Satriano (FG) e Castelluccio dei Sauri (FG) | Agrovoltaica | 70,3 | SOCIETA’ FOTOVOLTAICO CINQUE S.r.l. | 18/11/2024 |
Verifica amministrativa
|
“Licata-Naro | Agrovoltaica | 82,2 | Solaria Promozione e Sviluppo Fotovoltaico S.r.l. | 18/11/2024 |
Verifica amministrativa
|
Ervesa | Agrovoltaica y almacenamiento | 90 | GRV Solar Salento 1 S.r.l. | 12/11/2024 |
Provvedimento Unico in materia Ambientale
|
Renovación parque eólico | Eólica | 61 | IVPC Srl | 13/11/2024 |
Provvedimento Unico in materia Ambientale
|
Repotenciación “Sant’Agata Wind Park” | Eólica | 72 | Fri-El S. Agata Srl | 11/11/2024 | |
Proyecto de parque eólico compuesto por 12 aerogeneradores con una potencia total de 43, 64 MW | Eólica | 43,6 | Ecopower Srl | 05/11 |
Valutazione Impatto Ambientale negativa
|
Progetto di un impianto eolico, costituito da 7 aerogeneratori di potenza 7,2 MW ciascuno, per una potenza totale pari a 50,4 MW e delle relative opere di connessione alla RTN, da realizzarsi nei Comuni di Bortigiadas, Tempio Pausania, Calangianus (SS) | Eólica | 50,4 | BORTIGIADAS ENERGIA S.R.L. | 18/11/2024 |
Verifica amministrativa
|
Macchitelli | Eólica | 72 | GRV WIND NISSA S.r.l. | 06/11/2024 |
Verifica amministrativa
|
Venti di Sassari | Eólica | 74,2 | NATURGY RINNOVABILI ITALIA S.R.L. | 20/11/2024 |
Verifica amministrativa
|
Progetto di un impianto eolico, di potenza pari a 36 MW, e relative opere di connessione alla RTN, da realizzarsi nei Comuni di Caccamo (PA), Alia (PA), Castronovo di Sicilia (PA) e Lercara Friddi (PA). | Eólica | 36 | RWE Renewables Italia S.r.l. | 18/11/2024 |
Verifica amministrativa
|
Progetto di un impianto eolico di potenza pari a 62 MWp, composto da 10 aerogeneratori aventi ciascuno una potenza nominale di 6,2 MW e delle relative opere di connessione alla RTN, da realizzarsi nei Comuni di Nurri (SU), Serri (SU), Isili (SU), Nurallao (SU), Genoni (SU). | Eólica | 62 | SARDEGNA NURRI 1 SRL | 07/11/2024 |
Verifica amministrativa
|
Conversano Wind | Eólica | 43,2 | SCS 38 S.r.l. | 19/11/2024 |
Verifica amministrativa
|
Progetto di un impianto eolico costituito da 6 aerogeneratori di potenza unitaria 7,2 MW, per una potenza complessiva di 43,2 MW e opere di connessione alla RTN, da realizzarsi nei Comuni di Castelvetrano (TP), Menfi (AG), Sambuca Di Sicilia (AG), Sciacca (AG). | Eólica | 43,2 | SIRIO QUATTRO S.R.L. | 18/11/2024 |
Verifica amministrativa
|
Progetto di un impianto eolico, costituito da 5 aereogeneratori di potenza 6,2 MW ciascuno, per una potenza totale di 31 MWp, integrato con sistema di accumulo da 8 MW e delle relative opere di connessione alla RTN, da realizzarsi nei Comuni di Isili, Nurallao, Nuragus, Genoni (SU) | Eólica y almacenamiento | 39 | Vento Solare S.r.l. | 14/11/2024 |
Verifica amministrativa
|
Progetto di un impianto fotovoltaico di potenza pari a 75,77 MW e delle relative opere di connessione alla RTN, da realizzarsi nei Comuni di Candela e Deliceto (FG). | Fotovoltaica | 75,7 | DUDAIM PROPCO S.R.L. | 08/11/2024 |
Verifica amministrativa
|
Apollo | Fotovoltaica | 17,8 | G SOLAR S.R.L. | 14/11/2024 |
Verifica amministrativa
|
Progetto di un impianto fotovoltaico di potenza di picco pari a 33.76 MW e relative opere di connessione alla RTN, da realizzarsi nei Comuni di Castellaneta e Ginosa (TA). | Fotovoltaica | 33,7 | SCHEMA 21 S.R.L. | 15/11/2024 |
Verifica amministrativa
|
FV Foggia | Fotovoltaico | 49,4 | LIMES 9 Srl | 04/11/2024 | |
IMPIANTO FOTOVOLTAICO A TERRA COLLEGATO ALLA RTN, località “Serra Taccori”,Comune di Uta (CA) | Fotovoltaico | 96,1 | DIOMEDE SRL | 06/11/2024 |
Valutazione Impatto Ambientale negativa
|