Spain takes a strategic step in consolidating renewable hydrogen. On 4 April, the Institute for the Diversification and Saving of Energy (IDAE) published the Final Resolution Proposal for the Incentives Programme for Renewable Hydrogen Production and Consumption Projects – Clusters or Valleys, under the Recovery, Transformation and Resilience Plan, funded by the European Union – NextGenerationEU.
A total of €1,223,093,691 in non-repayable grants is proposed for seven projects selected through a competitive tender process.
These initiatives will enable the installation of over 2,292.8 MW of electrolysis capacity (MWe) across six Spanish regions: Castile and León, Aragon, Galicia, Andalusia, Catalonia, and other high-potential industrial zones.
Repsol, Capital Energy, CIP and RIC Energy among the beneficiaries
Among the awardees is the CATALINA project, led by Copenhagen Infrastructure Partners (CIP), which will receive €245 million to deploy 500 MW of electrolysis in Andorra (Aragon).
Also notable is the Andalusian Green Hydrogen Valley, developed by MOEVE, which will obtain €303.75 million for 405 MW of capacity in Palos de la Frontera, Andalusia.
The P2X HOLDCO consortium, in collaboration with Repsol, will operate the Hydrogen Valley of A Coruña, comprising 251.8 MW of capacity, with an assigned subsidy of €170.2 million. The development will be located in Galicia, a strategic region for energy exports.
The Tarragona Hydrogen Network (T-HYNET), also led by Repsol, has been selected as well, with 140.8 MW and €104.2 million in funding, located in La Pobla de Mafumet (Catalonia).
Meanwhile, Capital Energy and ALKEYMIA GROUP will receive a total of €138.6 million for a transregional 360 MW project spanning the municipalities of Caspe, Fabara and Ascó, in Aragon and Catalonia.
The Sustainable Fuel Production Plant project in Cubillos del Sil, developed by RIC Energy, is another major recipient, with €81.4 million and 220 MW of electrolysers to be deployed in Castile and León.
Finally, the León Green Hydrogen Valley, managed by La Robla Green, has been earmarked for €180 million in financial support to develop 415.2 MW across La Robla and Villadangos del Páramo (Castile and León).
TABLA 1: Relación de solicitudes estimadas PARA LAS QUE SE PROPONE la concesión de la ayuda. | |||||||||||||||
Código del expediente
|
Título Proyecto
|
Localización Electrólisis
[Municipio – CCAA] |
Criterios de Puntuación |
Potencia Electrólisis [MWe]
|
NIF
Beneficiario |
Coste Subvencionable total
(€) |
Ayuda Propuesta Concesión (€)
|
||||||||
1.1 Ratio específico Ayuda Solicitada: [€/MWe] |
2.1. Grado de madurez del proyecto |
2.2. Solvencia técnica y experiencia de la empresa y del proyecto |
3.1. Impacto social y económico |
3.2. Impacto en reducción de emisiones y circularidad |
3.3. Proyectos para la mejora de la formación local y proyectos que incluyan actividades I+D |
3.4. Contribución a competitividad y resiliencia tecnológica e industrial del sector del hidrógeno renovable de la UE |
3.5. Cercanía geográfica producción y consumo del hidrógeno renovable o derivados del mismo |
Puntuación Total | |||||||
PR-H2CLUSTER-2024- 000074 | Planta de Producción de Combustible Sostenible de Aviación “COMPOSTILLA GREEN – PLANTA DE H2 y eSAF” |
Cubillos del Sil – CASTILLA Y LEÓN |
56.72 | 3.05 | 3.70 | 3.50 | 3.00 | 2.00 | 3.80 | 0.50 | 76.27 | 220.00 | RIC Energy | 632,474,369.95 € | 81,400,000.00 € |
PR-H2CLUSTER-2024- 000069* | Valles Leonés Del Hidrógeno Verde | La Robla, Villadangos del Páramo – CASTILLA Y LEÓN |
54.44 | 3.65 | 2.45 | 1.50 | 3.50 | 2.00 | 4.50 | 4.00 | 76.04 | 415.20 | La Robla Green | 371.000.000,00 € 341.000.000,00 € |
93.786.909,71 € 86.203.062,56 € |
PR-H2CLUSTER-2024- 000073 | Generación de H2 verde para Producir combustibles Derivados en el valle del río Ebro (HyBERUS) |
Caspe, Fabara, Ascó – ARAGÓN CATALUÑA |
56.18 | 2.58 | 2.60 | 0.75 | 2.20 | 1.50 | 2.10 | 4.00 | 71.91 | 360.00 | Capital Energy y ALKEYMIA GROUP | 172.632.355,97 € 126.710.578,00 € 3.000.000,00 € 2.050.000,00 € |
78.605.124,72 € 57.695.446,09 € 1.365.997,54 € 933.431,65 € |
PR-H2CLUSTER-2024- 000028* | CATALINA | Andorra – ARAGÓN | 52.41 | 3.55 | 2.50 | 2.25 | 3.00 | 2.00 | 2.50 | 0.50 | 68.71 | 500.00 | CI ETF I COOPERATIEF | 534,942,519.50 € | 245,000,000.00 € |
PR-H2CLUSTER-2024- 000044 | Valle del Hidrógeno de A Coruña | A Coruña – GALICIA | 45.74 | 3.10 | 2.90 | 2.00 | 3.25 | 2.50 | 3.00 | 4.00 | 66.49 | 251.80 | P2X HOLDCO Repsol |
369.418.542,00 € 116.550.000,00 € |
129.351.776,12 € 40.809.942,63 € |
PR-H2CLUSTER-2024- 000064 | Valle Andaluz Del Hidrógeno Verde: Proyecto ONUBA |
Palos de la Frontera – ANDALUCÍA |
43.08 | 3.13 | 3.25 | 2.50 | 3.25 | 3.00 | 2.60 | 4.00 | 64.81 | 405.00 | MOEVE | 736,594,666.06 € | 303,750,000.00 € |
PR-H2CLUSTER-2024- 000038* | Tarragona Hydrogen Network (T-HYNET) | La Pobla de Mafumet – CATALUÑA |
43.44 | 3.80 | 2.15 | 2.00 | 3.20 | 1.50 | 4.00 | 3.50 | 63.59 | 140.80 | Repsol | 314,883,873.40 € | 104,192,000.00 € |
Reserve list and rejected projects
The resolution also includes a reserve list of projects that, although meeting the minimum score threshold, have not been granted funding due to budget limitations. These could be supported in case of withdrawals or future budget extensions.
The four initiatives on the reserve list are promoted by Repsol, EDP España, and BP ENERGÍA ESPAÑA in partnership with Iberdrola and ITE.
TABLA 2: Relación de solicitudes estimadas PARA LAS QUE NO SE PROPONE la concesión de la ayuda – Lista de Espera. | |||||||||||||||
Código del expediente
|
Título Proyecto
|
Localización Electrólisis [Municipio – CCAA]
|
Criterios de Puntuación |
Potencia Electrólisis [MWe]
|
NIF
Beneficiario |
Coste Subvencionable total
(€) |
Ayuda Propuesta Concesión (€)
|
||||||||
1.1 Ratio específico Ayuda Solicitada: [€/MWe] |
2.1. Grado de madurez del proyecto |
2.2. Solvencia técnica y experiencia de la empresa y del proyecto |
3.1. Impacto social y económico |
3.2. Impacto en reducción de emisiones y circularidad |
3.3. Proyectos para la mejora de la formación local y proyectos que incluyan actividades I+D |
3.4. Contribución a competitividad y resiliencia tecnológica e industrial del sector del hidrógeno renovable de la UE |
3.5. Cercanía geográfica producción y consumo del hidrógeno renovable o derivados del mismo |
Puntuación Total | |||||||
PR-H2CLUSTER-2024- 000039 | ELECTROLIZADOR CARTAGENA FASE II | Cartagena – REGIÓN DE MURCIA |
42.36 | 2.25 | 3.15 | 2.50 | 3.00 | 0.50 | 4.20 | 3.50 | 61.46 | 100.00 | Repsol | 193,792,000.00 € | 77,000,000.00 € |
PR-H2CLUSTER-2024- 000045 | CHALLENGE 2.0 | Los Barrios, San Roque – ANDALUCÍA |
43.89 | 2.65 | 2.45 | 3.00 | 3.20 | 1.00 | 0.60 | 4.00 | 60.79 | 274.99 | EDP España | 316,075,756.46 € | 199,992,728.02 € |
PR-H2CLUSTER-2024- 000010 | Proyecto gH2 Castellón fase II | Castelló de la Plana – COMUNITAT VALENCIANA |
20.46 | 3.55 | 2.45 | 2.25 | 4.00 | 2.00 | 4.30 | 4.00 | 43.01 | 105.00 | BP ENERGIA ESPAÑA Iberdrola ITE | 103.039.627,79 € 126.840.000,00 € 8.770.372,21 € 50.000,00 € |
62.548.982,26 € 76.996.715,54 € 5.323.950,29 € 30.351,91 € |
PR-H2CLUSTER-2024- 000017 | COLÓN – Clúster Onubense deL hidrÓgeno reNovable |
Palos de la Frontera – ANDALUCÍA |
16.15 | 4.05 | 2.45 | 2.50 | 3.00 | 2.00 | 2.70 | 4.00 | 36.85 | 120.00 | Iberdrola INNOMERICS |
240.409.752,00 € 161.900,00 € |
179.878.863,53 € 121.136,47 € |
In addition, five projects were rejected for failing to meet technical or environmental criteria — particularly the lack of firm offtake agreements for at least 60% of the hydrogen produced, electrolyser sites below the minimum 50 MW, or non-compliance with the DNSH principle (Do No Significant Harm).
The following companies were listed among the rejected proposals: FYM, Petronor, EDF, EDP España, Rolwind (Hyren Almonte), Solarig Global Services, Forestal del Atlántico and Reganosa.
TABLA 3: Relación de solicitudes desestimadas, por no alcanzar la puntuación mínima exigida en alguno de los criterios excluyentes. | |||||||||||||
Código del expediente
|
Título Proyecto
|
Localización Electrólisis
[Municipio – CCAA] |
Criterios de Puntuación |
NIF
Beneficiario |
Motivos
|
||||||||
1.1 Ratio específico Ayuda Solicitada: [€/MWe] |
2.1. Grado de madurez del proyecto |
2.2. Solvencia técnica y experiencia de la empresa y del proyecto |
3.1. Impacto social y económico |
3.2. Impacto en reducción de emisiones y circularidad |
3.3. Proyectos para la mejora de la formación local y proyectos que incluyan actividades I+D |
3.4. Contribución a competitividad y resiliencia tecnológica e industrial del sector del hidrógeno renovable de la UE |
3.5. Cercanía geográfica producción y consumo del hidrógeno renovable o derivados del mismo |
Puntuación Total | |||||
PR-H2CLUSTER-2024- 000030 | PRODUCCIÓN DE H2 VERDE A GRAN ESCALA INDUSTRIAL EN BILBAO (HERMES) | Arrigorriaga – PAÍS VASCO | 48.16 | 1.75 | 2.45 | 0.25 | 2.00 | 1.50 | 4.20 | 4.00 | N / A | FyM Petronor EDF | No alcanza la puntuación mínima de 5 puntos en los criterios técnicos, excluyentes según el art.15.6 de las Bases Reguladoras. |
PR-H2CLUSTER-2024- 000046 | GH2 SOTO 250 | Ribera de Arriba – PRINCIPADO DE ASTURIAS |
48.46 | 0.75 | 1.95 | 3.75 | 2.70 | 1.00 | 0.60 | 2.50 | N / A | EDP ESPAÑA | No alcanza la puntuación mínima de 5 puntos en los criterios técnicos, excluyentes según el art.15.6 de las Bases Reguladoras. |
PR-H2CLUSTER-2024- 000063 | ROCIOH2 | Almonte – ANDALUCÍA | 44.36 | 2.00 | 1.80 | 1.25 | 3.50 | 0.00 | 2.80 | 0.00 | N / A | ROLWIND (HYREN ALMONTE) | No alcanza la puntuación mínima de 5 puntos en los criterios técnicos y 10 puntos en los criterios ambientales y socioeconómicos, excluyentes según el art.15.6 de las Bases Reguladoras. |
PR-H2CLUSTER-2024- 000071 | Turboleta SAF | Teruel – ARAGÓN | 36.26 | 1.75 | 3.05 | 1.25 | 2.80 | 0.00 | 2.30 | 0.50 | N / A | SOLARIG GLOBAL SERVICES | No alcanza la puntuación mínima de 5 puntos en los criterios técnicos y 10 puntos en los criterios ambientales y socioeconómicos, excluyentes según el art.15.6 de las Bases Reguladoras. |
PR-H2CLUSTER-2024- 000012 | ValdoEume | Mugardos, As Pontes de García Rodríguez – GALICIA |
0.00 | 3.26 | 1.15 | 3.00 | 1.90 | 2.00 | 2.10 | 2.00 | N / A | FORESTAL DEL ATLANTICO REGANOSA |
No alcanza la puntuación mínima de 5 puntos en los criterios técnicos, excluyentes según el art.15.6 de las Bases Reguladoras. |
Evaluation criteria and budget allocation
The evaluation process was based primarily on economic criteria (up to 70 points), technical capacity (10 points), and environmental and socio-economic impact (20 points).
Priority was given to projects that optimise the public aid per MW installed, demonstrate strong technical maturity, and generate local impact, job creation, gender equality and sustainability.
Each project was required to have a minimum total capacity of 100 MW, with individual sites of at least 50 MW and no more than 100 km apart to be considered as a single hydrogen valley. In addition, firm offtake agreements for at least 60% of the hydrogen or its derivatives were mandatory.
This first call was endowed with a total budget of €1.2 billion, of which a substantial portion has been committed in this phase. No single company or project may receive more than 33% of the available funds, ensuring fair distribution.
Next steps and deadlines
Awarded entities must formally accept the grant within ten working days of publication. Failure to do so will be considered an automatic withdrawal. The final resolution will then be submitted to the IDAE Board of Directors for approval.
Subsidised actions must be completed within 36 months from the date of the grant resolution. Eligible investments must have started after 9 March 2023, in accordance with the incentive effect criteria.
0 Comments